Sizewell A (left) and Sizewell B (right), two generations of British nuclear power on the Suffolk coast

Sizewell A (left) and Sizewell B (right), two generations of British nuclear power generation on the Suffolk coast

Why is it proving so difficult to close the deal on new nuclear in Britain? In part, of course, there is the normal arm wrestling negotiation. This is focused on the so called “strike price” – an energy price below which the suppliers will get compensation from the state – and on the allocation of risk around a £14bn construction contract.

The UK government wants a strike price of around £65 to £70 per MWh which is high but probably politically defensible. They well remember that in 2008 EDF talked about a price of £45 per MWh. EDF now wants something between £95 and £100, but they can probably afford to accept the Government’s figure and still make a reasonable profit.

The allocation of the risks is even more important than the strike price. Unless the Government is careful it could end up pay enormous sums for capacity which is underused because cheaper supplies will be available to consumers. If the company gets it wrong, a bad deal would overhang its finances for decades. Read more